Baron Residence Construction Progress (2nd Phase Development)

JULY 2024

Baron Residence Progress Update: Topped Out

We are pleased to announce that the project has reached a significant milestone: the structural framework has been topped out.

This achievement marks a crucial phase in the construction process, and we extend our gratitude to all team members and partners for their dedication and hard work.

Baron Residence
Baron Residence
Baron Residence

(Photos taken on 8th July 2024)

JUNE 2024

Block A – Completed 2A, 2B on floor 34th, 2D on floor 26th

Block B – Completed 2A, 2B on floor 36th, 2D on floor 26th

Block C – Completed 2A, 2B on floor 36th, 2D on floor 26th

Baron Residence
Baron Residence
Baron Residence

(Photos were taken on 05/06/2024.)

MAY 2024

Block A – Completed 2A, 2B on floor 28th, 2C on floor 17th, 2D on floor 20th.
Block B – Completed 2A, 2B on floor 30th, 2C on floor 18th, 2D on floor 20th.
Block C – Completed 2A, 2B on floor 30th, 2C on floor 18th, 2D on floor 20th.

Baron Residence
Baron Residence
Baron Residence

(Photos were taken on 06/05/2024.)

APRIL 2024

Lake City’s 2nd Phase Development- Baron Residence progress update. 🏗

Block A – Completed 2A, 2B on floor 23th, 2C on floor 13th, 2D on floor 13th

Block B – Completed 2A, 2B on floor 25th, 2C on floor 14th, 2D on floor 13th

Block C – Completed 2A, 2B on floor 25th, 2C on floor 14th, 2D on floor 13th

Baron Residence
Baron Residence
Baron Residence

(Photos were taken on 5th April 2024.)

MARCH 2024

Lake City’s 2nd Phase Development- Baron Residence progress update. 🏗

Block A – Completed 2A, 2B on floor 18th, 2C on floor 13th, 2D on floor 10th

Block B – Completed 2A, 2B on floor 19th, 2C on floor 14th, 2D on floor 10th

Block C – Completed 2A, 2B on floor 20th, 2C on floor 14th, 2D on floor 10th

Baron Residence
Baron Residence

(Photos were taken on 2nd March 2024.)

JAN 2024

Lake City’s 2nd Phase Development- Baron Residence progress update. 🏗

Block A – Completed 2A, 2B on floor 8th, 2C on floor 3th, 2D on floor 3th.

Block B – Completed 2A, 2B on floor 9th, 2C on floor 3th, 2D on floor 3th.

Block C – Completed 2A, 2B on floor 10th, 2C on floor 4th, 2D on floor 4th.

Baron Residence

(Photos were taken on 16th Jan 2024.)

2023.Nov

Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A & 2B on floor 5th
Block B – Completed 2A & 2B on floor 6th
Block C – Completed 2A & 2B on floor 6th

https://www.facebook.com/profile.php?id=100089612787384
Baron Residence @Lake City(2nd Phase Construction Progress)
Kepong hot selling property with waterfront smart community
Lake City Township 1st Phase & 2nd phase Development @ Kepong


2023.Oct

Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A & 2B on floor 1st
Block B – Completed 2A & 2B on floor 2nd
Block C – Completed 2A & 2B on floor 3rd

甲洞 湖景 公寓 城市 发展
Waterfront mix development at kepong

2023. AUG

Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A ;
Block B – Completed 2A ;
Block C – Completed 2A & 2B on floor 1st