JULY 2024
Baron Residence Progress Update: Topped Out
We are pleased to announce that the project has reached a significant milestone: the structural framework has been topped out.
This achievement marks a crucial phase in the construction process, and we extend our gratitude to all team members and partners for their dedication and hard work.
(Photos taken on 8th July 2024)
JUNE 2024
Block A – Completed 2A, 2B on floor 34th, 2D on floor 26th
Block B – Completed 2A, 2B on floor 36th, 2D on floor 26th
Block C – Completed 2A, 2B on floor 36th, 2D on floor 26th
(Photos were taken on 05/06/2024.)
MAY 2024
Block A – Completed 2A, 2B on floor 28th, 2C on floor 17th, 2D on floor 20th.
Block B – Completed 2A, 2B on floor 30th, 2C on floor 18th, 2D on floor 20th.
Block C – Completed 2A, 2B on floor 30th, 2C on floor 18th, 2D on floor 20th.
(Photos were taken on 06/05/2024.)
APRIL 2024
Lake City’s 2nd Phase Development- Baron Residence progress update.
Block A – Completed 2A, 2B on floor 23th, 2C on floor 13th, 2D on floor 13th
Block B – Completed 2A, 2B on floor 25th, 2C on floor 14th, 2D on floor 13th
Block C – Completed 2A, 2B on floor 25th, 2C on floor 14th, 2D on floor 13th
(Photos were taken on 5th April 2024.)
MARCH 2024
Lake City’s 2nd Phase Development- Baron Residence progress update.
Block A – Completed 2A, 2B on floor 18th, 2C on floor 13th, 2D on floor 10th
Block B – Completed 2A, 2B on floor 19th, 2C on floor 14th, 2D on floor 10th
Block C – Completed 2A, 2B on floor 20th, 2C on floor 14th, 2D on floor 10th
(Photos were taken on 2nd March 2024.)
JAN 2024
Lake City’s 2nd Phase Development- Baron Residence progress update.
Block A – Completed 2A, 2B on floor 8th, 2C on floor 3th, 2D on floor 3th.
Block B – Completed 2A, 2B on floor 9th, 2C on floor 3th, 2D on floor 3th.
Block C – Completed 2A, 2B on floor 10th, 2C on floor 4th, 2D on floor 4th.
(Photos were taken on 16th Jan 2024.)
2023.Nov
Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A & 2B on floor 5th
Block B – Completed 2A & 2B on floor 6th
Block C – Completed 2A & 2B on floor 6th
2023.Oct
Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A & 2B on floor 1st
Block B – Completed 2A & 2B on floor 2nd
Block C – Completed 2A & 2B on floor 3rd
2023. AUG
Baron Residence (2nd Phase Work Progress)
Block A – Completed 2A ;
Block B – Completed 2A ;
Block C – Completed 2A & 2B on floor 1st